PAS 2030 vs PAS 2035. What’s the Difference?

Standards for Retrofit Installers and Retrofit Services
19 October 2026 by
Joseph Nelson

Understanding the difference between retrofit installation and the wider whole-house process

PAS 2030 and PAS 2035 are two of the most important standards in domestic energy retrofit, but they are frequently confused.

The numbers are similar. They are commonly mentioned together. The same retrofit project will often need to comply with both.

But they perform very different functions.

The simplest way to understand the distinction is:

PAS 2035 is about the property and the overall retrofit process.

PAS 2030 is about the installation of the energy efficiency measures.

PAS 2035 covers the wider journey: assessing the dwelling, identifying appropriate improvements, designing them, coordinating the project and evaluating the completed retrofit.

PAS 2030 sets requirements for how energy efficiency measures are installed, including installation processes, workmanship-related controls, competence, commissioning and measure-specific requirements. BSI describes PAS 2030 as specifying requirements for installation of energy efficiency measures in existing dwellings, while PAS 2035 provides the end-to-end framework for domestic retrofit.

They are different standards, but they are deliberately designed to work together.

For installers, housing providers and clients, understanding where one stops and the other starts is essential.

At PAS2035 Consultants Ltd, this distinction is particularly important because our work primarily sits on the PAS 2035 professional side of the process: Retrofit Design, Retrofit Coordination and wider technical consultancy.

The installation company remains responsible for its own PAS 2030 certification, competence and installation obligations.

What Is PAS 2035?

PAS 2035 is the overarching standard for the energy retrofit of existing domestic buildings.

It establishes a structured process intended to move retrofit away from simply installing isolated measures and towards considering the whole dwelling.

BSI describes PAS 2035 as setting out best practice for end-to-end energy efficiency and whole-house retrofit.

That distinction is important.

Imagine a property is going to receive External Wall Insulation.

If we only considered the insulation product itself, the project might appear straightforward.

But what happens to the windows?

What happens at the eaves?

What happens around ventilation terminals?

What happens at the damp-proof course?

What happens where the insulation meets an extension?

What happens to existing services?

Does the property have defects that need addressing first?

What effect will the work have on ventilation and airtightness?

Are there heritage considerations?

PAS 2035 creates a process through which those wider questions can be considered before and during the work.

It is therefore primarily concerned with making sure the right retrofit is properly assessed, planned, designed, coordinated and evaluated.

What Does PAS 2035 Cover?

The PAS 2035 process begins before an installer starts work.

It includes the Retrofit Assessment, which establishes information about the existing property.

That information feeds into consideration of defects, Intended Outcomes and potential improvements.

An Improvement Option Evaluation considers suitable energy efficiency measures.

A Medium-Term Improvement Plan can establish how the dwelling could be improved over time rather than assuming every measure needs to be completed in a single project.

The selected measures then need to form part of a proper Retrofit Design.

The project is overseen through Retrofit Coordination, with requirements around installation, handover, monitoring and evaluation completing the process.

BSI identifies assessment, identification and evaluation of improvement options, design and specification, monitoring and evaluation, and advice to occupants among the matters addressed by PAS 2035.

PAS 2035 is therefore much broader than an installation standard.

It is the framework surrounding the retrofit.

Who Works Under PAS 2035?

PAS 2035 introduces and defines several professional retrofit functions.

These include the:

Retrofit Assessor

Retrofit Designer

Retrofit Coordinator

and, where applicable, the Retrofit Evaluator.

The Retrofit Assessor gathers and records information about the existing property.

The Retrofit Designer converts the assessment and retrofit strategy into the technical solution.

The Retrofit Coordinator oversees the wider process and ensures that the different elements are brought together.

These functions are fundamentally different from the role of the Retrofit Installer.

And that brings us to PAS 2030.

What Is PAS 2030?

PAS 2030 deals specifically with the installation of energy efficiency measures in existing dwellings.

The current standard covers requirements relating to installation processes, process management and service provision. It also addresses installation methods, equipment, tools, suitability of products and materials, commissioning, and the training, skills and vocational qualifications of people undertaking installations.

It contains core requirements as well as measure-specific normative annexes.

Those annexes are important because installing External Wall Insulation is not the same activity as installing Loft Insulation, Underfloor Insulation or other retrofit measures.

Different measures require different competencies, processes and technical controls.

PAS 2030 therefore focuses much more closely on the organisation and people physically delivering the measure.

An Easy Way to Remember the Difference

Think of a retrofit project as building a bridge.

PAS 2035 determines:

Where should the bridge go?

What does it need to achieve?

What conditions exist at the site?

How should it be designed?

How do the different elements work together?

Who oversees the overall project?

PAS 2030 is concerned with:

How is the bridge actually constructed correctly?

Domestic retrofit is obviously different, but the distinction is useful.

Another simple way of putting it is:

PAS 2035 = Assess, Plan, Design and Coordinate

PAS 2030 = Install

There is more detail behind both standards, but this distinction explains their fundamental relationship.

Why Are PAS 2030 and PAS 2035 Always Mentioned Together?

Because they are intentionally interconnected.

BSI describes the two standards as effectively intended to be used in conjunction with one another for domestic retrofit. Designs prepared in accordance with PAS 2035 are required to be installed, commissioned and handed over in accordance with PAS 2030, or in specified cases through the relevant MCS standards. PAS 2030 users are correspondingly required to work to designs conforming to PAS 2035.

BSI has previously described the standards as being "locked together": PAS 2035 provides the wider retrofit framework and compliant design, while PAS 2030 provides the installation requirements.

That relationship is the key to understanding the system.

A good design badly installed is not good retrofit.

Equally, excellent workmanship cannot compensate for an inappropriate design.

The standards address different sides of the same problem.

The Retrofit Designer Does Not Replace the PAS 2030 Installer

This is an especially important distinction for project responsibilities.

A Retrofit Designer might specify how External Wall Insulation should interact with windows, doors, rooflines, services and adjoining elements.

They may produce specifications, drawings, junction details, ventilation requirements and other technical information.

But the designer does not become responsible for the installation company's PAS 2030 obligations simply because they designed the work.

Likewise, the Retrofit Coordinator may oversee the overall project, review information and identify non-compliance.

That does not make the Coordinator the PAS 2030 installer.

TrustMark states that products, components and systems incorporated into a PAS 2035 project must be specified within a design by the competent PAS 2035 designer. Those measures must then be installed by a competent installer certified by a UKAS-accredited Certification Body against the relevant PAS 2030 measure annex. TrustMark

The responsibilities need to remain clear.

PAS 2030 Certification Belongs to the Installer

An installation business wishing to undertake applicable PAS 2030 work needs the appropriate certification for the measures it intends to install.

It is not sufficient for the project to simply have a Retrofit Coordinator.

It is not sufficient to employ a PAS 2035 consultant.

And it is not sufficient for someone else within the supply chain to hold PAS 2030 certification.

The installer undertaking the relevant work needs to operate within its appropriate certified scope.

This is particularly important when installers first enter publicly funded retrofit.

A contractor may be extremely experienced in general construction, insulation or heating work.

That does not automatically mean the business is PAS 2030 certified.

Certification involves the appropriate certification route and demonstration that the business satisfies the applicable requirements.

PAS2035 Consultants can help installers understand how their work fits into the wider PAS 2035 process, but we cannot provide an installer's PAS 2030 accreditation on its behalf.

That remains the installer's responsibility.

PAS 2035 Is Not an Installer Accreditation

The opposite misunderstanding is equally common.

PAS 2035 should not simply be thought of as another installer certificate.

It is the wider process under which the retrofit is developed and managed.

For a typical PAS 2035 project, information might flow something like this:

Retrofit Assessment

↓

Defects and Intended Outcomes

↓

Improvement Option Evaluation

↓

Medium-Term Improvement Plan

↓

Retrofit Design

↓

Pre-Installation Checks

↓

PAS 2030 Installation

↓

Quality Assurance and Evidence

↓

Handover

↓

Monitoring and Evaluation

The installation sits within the process.

It does not replace the process.

Where Does TrustMark Fit In?

TrustMark provides an important part of the quality framework surrounding government-supported domestic retrofit.

Its Retrofit Portal and Data Warehouse provide the infrastructure through which applicable PAS 2035 projects and evidence are managed and lodged.

Following the transition from the 2019 standards, TrustMark states that PAS 2030:2023 projects must originate from a PAS 2035:2023 assessment. It also introduced new PAS 2030:2023 installer trade codes alongside the updated retrofit process.

This demonstrates how closely the two standards are connected operationally.

The professional PAS 2035 process establishes the project.

The PAS 2030 installer delivers the relevant measure.

Evidence from those different functions ultimately needs to come together to demonstrate a completed retrofit.

Design Versus Installation

One of the easiest places to see the distinction is at the boundary between the Retrofit Designer and Retrofit Installer.

Suppose a property is receiving External Wall Insulation.

The PAS 2035 design might establish matters such as:

  • extent of insulation;
  • insulation specification;
  • treatment of junctions;
  • relationship with windows and doors;
  • roofline interfaces;
  • services requiring consideration;
  • ventilation requirements;
  • airtightness requirements;
  • treatment of identified defects;
  • relevant enabling works; and
  • property-specific constraints.

The PAS 2030 installer then needs to install the measure correctly in accordance with the applicable design and installation requirements.

The designer tells the project what needs to be achieved and provides the technical design.

The installer turns that design into completed work.

Neither function is optional simply because the other has been performed well.

Why Good Information Between PAS 2035 and PAS 2030 Matters

There is a potential weak point in this system.

The handover between design and installation.

A technically excellent design is of limited practical value if the people installing the measure cannot easily identify the information relevant to their property.

This is one reason PAS2035 Consultants places considerable emphasis on the Site Installation Document (SID) within our Retrofit Design process.

A complete project file may contain a very large amount of information.

Assessment reports, photographs, drawings, specifications, product information and technical documents can easily run into dozens or even hundreds of pages.

That may be necessary for the overall project.

But it is not necessarily the best way to communicate with a site manager.

Our SID therefore extracts the key property-specific installation information into a concise, typically 2–5 page, image-heavy site document.

It can highlight defects and remediation, measure-specific requirements, relevant tenant information, conservation or flood considerations, the short-form ventilation strategy, important details, floor plans and elevations.

This creates a practical bridge between PAS 2035 Design and PAS 2030 Installation.

The Installer Still Needs the Full Requirements

The SID does not replace PAS 2030.

Nor does it replace manufacturer instructions, certification requirements or the complete Retrofit Design.

Its purpose is communication.

A site manager can quickly understand:

What are we installing?

What is unusual about this property?

What defects need addressing?

What are the critical design requirements?

Where are the measures going?

What do I particularly need to check?

The installer then combines that property-specific information with its own PAS 2030 processes, system requirements and installation competence.

That is how the two sides should work together.

What Happens if the Installer Finds Something Unexpected?

Existing buildings inevitably contain surprises.

Once work begins, the installer might discover that the property differs from the information available at design stage.

That does not mean the installer should simply improvise a new design.

Instead, there should be a clear feedback route.

Installer identifies issue → Retrofit Coordinator reviews → Designer provides technical input where required → agreed solution returns to installer.

This is another reason good Retrofit Coordination matters.

The Coordinator acts as the link between the professional design process and site delivery.

It allows installation issues to be resolved without blurring professional responsibilities.

Where PAS2035 Consultants Fits

PAS2035 Consultants primarily operates on the PAS 2035 side of this relationship.

Depending on the project, we can provide or organise the professional functions required around:

Retrofit Design

Retrofit Coordination

Assessment through trusted assessment partners

Technical consultancy and project oversight

Ventilation and airtightness strategies

Heritage, flood and other additional design requirements where applicable

Site Installation Documents

Quality assurance and completion review

This allows us to work alongside established PAS 2030 installers rather than trying to replace their function.

An installer may already have excellent installation teams and appropriate certification but not want to maintain a large internal Design and Coordination department.

We can provide that professional layer.

Alternatively, a housing provider may appoint PAS2035 Consultants independently to provide technical oversight while separate installation contractors undertake the physical measures.

Both models can create a clear division of responsibility.

Why External PAS 2035 Support Can Add Value

There is also a wider benefit to separating the technical oversight of a retrofit from the commercial pressure to install measures.

BSI's retrofit guidance has highlighted the importance of managing conflicts of interest and has recommended that Retrofit Coordinators work for householders or landlords rather than retrofit contractors where possible.

That does not mean an installer-linked model is automatically non-compliant.

But independent PAS 2035 oversight can provide a useful additional layer of assurance.

The Designer can ask whether the proposed solution is appropriate.

The Coordinator can ask whether the PAS 2035 process has been properly followed.

The PAS 2030 installer can concentrate on delivering the work correctly.

Everyone has a clear role.

PAS 2030 and PAS 2035 in One Sentence

If there is only one thing to remember from this article, it is this:

PAS 2035 establishes what retrofit should be undertaken, how it should be assessed, designed and coordinated; PAS 2030 establishes requirements for how the specified energy efficiency measures are installed.

They are not competing standards.

They are complementary.

BSI's current PAS 2030 scope makes this particularly clear: PAS 2030 applies to organisations installing products or systems designed to improve the energy efficiency of existing dwellings in accordance with PAS 2035:2023.

Two Standards, One Retrofit

Good retrofit requires more than good installation.

It also requires more than good design.

A home needs to be properly understood before work begins.

Appropriate measures need to be identified.

Those measures need to be designed around the actual building.

Interactions between measures need to be considered.

Defects need to be identified and addressed.

The installer needs clear information.

The measures need to be competently installed.

And the completed project needs to be checked, evidenced and handed over.

That is why PAS 2030 and PAS 2035 work together.

PAS 2035 provides the framework.

PAS 2030 provides the installation requirements.

At PAS2035 Consultants Ltd, our role is to help make the PAS 2035 side of that relationship work in practice: producing clear Retrofit Designs, coordinating projects, providing practical site information and working constructively with PAS 2030 installers.

We can help an installer understand the project.

We can provide the design they need to work from.

We can coordinate the wider PAS 2035 process.

We can help ensure information flows properly between assessment, design, site and completion.

But the distinction remains important:

PAS2035 Consultants is responsible for the professional PAS 2035 services within our appointment. The installer remains responsible for its own PAS 2030 certification, competence, processes and workmanship.

When those responsibilities are clear and both sides communicate effectively, PAS 2030 and PAS 2035 stop looking like two confusing numbers.

They become what they were intended to be:

two interconnected parts of a structured approach to delivering better domestic retrofit.

For the underlying standards and current guidance, see BSI's PAS 2035 overview, BSI's PAS 2030 overview and TrustMark's PAS 2035 guidance

Joseph Nelson 19 October 2026