2035 Retrofit Process: From Assessment to Completion

The Retrofit process summarised
19 October 2026 by
Joseph Nelson

How PAS 2035 takes a home from assessment through design, installation and handover

Domestic retrofit is not simply a case of choosing an insulation measure, appointing an installer and starting work. Changes to one part of a home can affect ventilation, moisture, heating demand, thermal bridging, building fabric and the performance of other measures.

PAS 2035 provides a structured process for managing those interactions.

Under PAS 2035:2023, a retrofit project progresses through assessment, evaluation of improvement options, development of a Medium-Term Improvement Plan, design, installation, handover and evaluation. The objective is to create a coordinated whole-dwelling approach, rather than treating individual energy efficiency measures in isolation. BSI

At PAS2035 Consultants Ltd, our role is to help clients, housing providers and installers navigate this process efficiently while maintaining the separation of professional responsibilities required by the standards.

Importantly, PAS 2035 consultancy does not replace the installer’s responsibilities under PAS 2030. Where PAS compliance is required, the relevant measures must be installed by appropriately competent and certified installers. TrustMark states that an installer must be certified by a UKAS-accredited Certification Body against the relevant PAS 2030 measure annex applicable to the work being undertaken. 

So how does a property actually move from its first assessment to a completed retrofit project?

1. Starting with the Retrofit Assessment

The first major stage is understanding the dwelling as it actually exists.

A Retrofit Assessment establishes the information required to make informed decisions about improvements. It is considerably more than simply obtaining an EPC.

The assessment considers the property's construction, condition, energy performance, ventilation and other relevant characteristics. Existing defects are particularly important because retrofit should not conceal or exacerbate problems such as damp, water penetration or inadequate ventilation.

Under the TrustMark lodgement process for PAS 2035:2023, the assessment feeds into the identification of defects, intended outcomes, evaluation of improvement options, Medium-Term Improvement Plan and eventual retrofit design. 

This creates one of the fundamental principles of PAS 2035:

Understand the building before designing the intervention.

A good assessment therefore provides the foundation for everything that follows. Poor or incomplete information at this stage can create problems much later, when designers or installers discover that the actual property differs from what was originally assumed.

At PAS2035 Consultants, we can work with project teams to establish clear assessment requirements and review the information available before projects progress into detailed design.

2. Identifying Defects and Constraints

Before deciding what should be installed, the existing condition of the property needs to be considered.

For example, a proposal for wall insulation might be affected by:

  • damp or water penetration;
  • defective rainwater goods;
  • inadequate ventilation;
  • unsuitable existing finishes;
  • structural defects;
  • roof or junction details;
  • existing services;
  • heritage significance; or
  • limitations created by previous alterations.

PAS 2035:2023 also gives greater structure to how certain issues are recorded within the TrustMark process. For example, where existing or combustion ventilation is identified as inadequate, the Retrofit Portal requires the ventilation defect and its proposed resolution to be addressed at design stage. 

This is where early professional input can save considerable time.

Identifying an issue after an installer arrives on site can result in delays, redesign and additional cost. Identifying it during assessment and design allows it to become part of the planned project.

3. Agreeing the Intended Outcomes

Retrofit should have a purpose.

The project team therefore needs to establish what the retrofit is intended to achieve.

Depending on the project, intended outcomes could relate to improved energy performance, reduced energy demand, improved comfort, resolution of existing building issues or achievement of the requirements of a particular funding programme.

TrustMark's PAS 2035:2023 process specifically includes agreeing the Intended Outcomes with the property owner before evaluating the improvement options and developing the project. 

This helps prevent retrofit becoming a collection of disconnected measures.

Instead, each measure should contribute towards an agreed objective for the dwelling.

For larger programmes, this stage is particularly valuable. PAS2035 Consultants can help clients establish a consistent approach to intended outcomes across a portfolio while still recognising that individual properties may require different solutions.

4. Improvement Option Evaluation

Once the property and project objectives are understood, the available improvement options can be considered.

This is the Improvement Option Evaluation (IOE).

The purpose is not simply to create the longest possible list of energy improvements. Measures need to be considered in the context of the particular dwelling, its occupants, its condition and the interactions between different improvements.

For example, increasing airtightness or adding insulation can alter the ventilation requirements of a dwelling. Installing one measure today can also make another measure more difficult or expensive in the future.

PAS 2035 therefore requires a whole-dwelling approach.

This is an important difference between coordinated retrofit and isolated home improvement.

5. The Medium-Term Improvement Plan

The Improvement Option Evaluation feeds into the Medium-Term Improvement Plan (MTIP).

The MTIP provides a longer-term route for improving the property, even where every recommended measure will not be installed as part of the current project.

PAS 2035:2023 requires the plan to consider the building's history, construction, architectural character, setting and use. It should identify appropriate improvements and enabling works, consider interactions between measures and establish an appropriate sequence for installation. BSI

That sequencing can be extremely important.

For example, future wall insulation, window replacement, roof works, ventilation improvements and heating upgrades can interact. Thinking ahead can avoid completing work now that subsequently has to be altered or removed.

The standard also requires the MTIP to be capable of being updated as work progresses and as technologies or knowledge change. BSI

The result is effectively a roadmap for the dwelling rather than a one-off specification.

6. Agreeing the Actual Project

The Medium-Term Improvement Plan may identify a range of potential improvements, but that does not necessarily mean all of them will be installed immediately.

The Retrofit Coordinator reviews the improvement options, proposed packages and MTIP with the client and agrees the scope, intended outcomes, appropriate energy performance targets and budget for the actual project. BSI

This creates the bridge between long-term strategy and practical delivery.

For a housing provider managing hundreds of homes, for example, the MTIP may establish the direction of travel for each property while the current funded programme delivers only part of that journey.

The important point is that today's work is considered in the context of tomorrow's improvements.

7. Retrofit Design

Once the scope has been established, the proposed measures need to be properly designed.

PAS 2035:2023 requires the Retrofit Coordinator to verify that the measures included in the project are incorporated into a retrofit design prepared by a Retrofit Designer. BSI

This is a critical stage.

A compliant retrofit design should translate assessment information and project objectives into information that can actually be constructed.

Depending on the measures involved, this may include:

  • specifications and products;
  • drawings and construction details;
  • junction and thermal-bridge details;
  • ventilation requirements;
  • moisture-risk considerations;
  • interfaces between measures;
  • treatment of existing defects;
  • enabling works;
  • relevant Building Regulations requirements; and
  • installation requirements.

TrustMark's PAS 2035:2023 Design Best Practice Guidance emphasises that the designer needs sufficient information from the Retrofit Assessment, Pre-Installation Building Inspection, pre-design surveys and other technical assessments before preparing the design. It also identifies relevant PAS 2030 measure-specific annexes, system installation guidance, Agrément Certificate requirements, applicable standards and Building Regulations as part of the design context. 

Where PAS2035 Consultants can add value

This is an area where early involvement can substantially improve project delivery.

PAS2035 Consultants can provide Retrofit Design and Retrofit Coordination services, helping to create a clear link between the assessment, proposed measures and the information the installer needs on site.

Rather than treating compliance as paperwork completed after installation, the aim is to establish the requirements before work starts.

That can reduce queries, redesign, aborted installations and disputes over what was expected.

8. Pre-Installation Checks

There can be a significant period between assessment and installation.

Conditions can change. Additional information may become available. The installer may identify practical constraints that were not visible during the original survey.

PAS 2035:2023 therefore incorporates the Pre-Installation Building Inspection (PIBI) within the process, and TrustMark identifies PIBI as a specific part of its 2023 Retrofit Portal arrangements. 

This creates an important final checkpoint before installation.

Where something has changed or additional information is identified, the correct approach is to resolve it before simply proceeding with work that may no longer reflect the property.

9. PAS 2030 and the Installer's Responsibilities

This distinction is particularly important.

PAS 2035 governs the overall retrofit process. PAS 2030 establishes requirements associated with installation of energy efficiency measures.

PAS2035 Consultants can assess, coordinate and design a project within the scope of the services appointed to us, but this does not transfer the installer's PAS 2030 responsibilities to the consultant.

TrustMark is explicit that PAS 2035 must be used in conjunction with PAS 2030 and that products and systems specified within a PAS 2035 design must be installed by a competent installer. The installer must hold certification from a UKAS-accredited Certification Body for the relevant PAS 2030 measure annex. 

This means an installer remains responsible for ensuring that it:

  • holds the appropriate PAS 2030 certification for the measures it installs;
  • maintains that certification;
  • works within the scope of its certification;
  • follows applicable installation requirements;
  • provides the required installation evidence; and
  • complies with its own quality-management and certification obligations.

Appointing a Retrofit Coordinator or Retrofit Designer does not make an uncertified installer PAS 2030 compliant.

The strongest projects are therefore collaborative ones: assessment, coordination and design provide the framework, while competent PAS 2030 installers deliver the specified measures correctly on site.

10. Installation and Quality Assurance

Once the design is complete and pre-installation requirements have been satisfied, installation can begin.

Good communication between designer, coordinator and installer becomes particularly important at this point.

Existing buildings rarely behave exactly like drawings.

Opening up works may expose unexpected construction. Junctions may differ from the survey information. Services may be located somewhere unexpected. An assumed substrate may turn out to be unsuitable.

The solution should not be uncontrolled deviation from the retrofit design.

Where a material change is required, it should be communicated and considered by the relevant professionals so that the implications for the overall retrofit strategy can be assessed.

PAS 2035 quality assurance also includes risk-based site oversight. TrustMark's current guidance identifies mandatory site-visit requirements for specified measures including EWI, IWI, room-in-roof insulation, underfloor insulation, park-home insulation and flat-roof insulation. 

For clients and housing providers, independent technical oversight can therefore provide a valuable connection between the design on paper and the work actually being delivered.

11. Handover and Completion

Installation is not the end of the PAS 2035 process.

The completed project needs to be properly handed over and evidenced.

Documentation may include installation records, photographs, commissioning information, guarantees, certificates and other project-specific evidence.

The TrustMark Data Warehouse process itself is structured around Assessment, Project and lodgement of the installed measures. 

A well-managed evidence process makes this considerably easier.

Waiting until the end of a programme to discover that photographs, commissioning records or installation evidence are missing can create unnecessary delays.

For this reason, PAS2035 Consultants can work with project teams to establish evidence requirements before installation begins and review information as projects progress.

12. Monitoring and Evaluation

PAS 2035 does not assume that successful installation automatically proves that every intended outcome has been achieved.

PAS 2035:2023 requires the Retrofit Coordinator to prepare a monitoring and evaluation plan appropriate to the measures included within the MTIP, including basic evaluation at the end of each stage of retrofit. BSI

This closes the loop.

The project begins by asking what the dwelling needs and what the retrofit should achieve. Evaluation then considers the completed work against those objectives.

That feedback can also improve future projects across larger housing programmes.

Making PAS 2035 Easier to Deliver

PAS 2035 can appear complicated when every role and document is considered separately.

In practice, the process becomes much easier when the stages are connected:

Assessment → Defects → Intended Outcomes → Improvement Options → Medium-Term Improvement Plan → Project Scope → Retrofit Design → Pre-Installation Checks → PAS 2030 Installation → Quality Assurance → Handover → Evaluation

The value of good Retrofit Coordination is not simply producing compliance documents. It is ensuring information flows between these stages and that decisions made at one stage do not create problems at another.

PAS2035 Consultants Ltd can support clients through Retrofit Assessment oversight, Retrofit Design, Retrofit Coordination, technical review, ventilation and overheating considerations, Building Regulations design considerations, evidence review, quality assurance and post-installation evaluation, depending on the requirements of the project.

For housing providers and delivery partners, this can provide an independent technical layer between programme objectives and installation.

For installers, it can provide a clear professional route for the PAS 2035 elements surrounding their work, allowing the installer to concentrate on competent delivery of the measures for which it is appropriately certified.

The responsibilities remain distinct.

PAS2035 Consultants can help make the journey from assessment to completion clearer, better coordinated and easier to manage. The installer remains responsible for its own PAS 2030 certification, competence, installation quality and obligations within the scope of its certification.

That separation of responsibility, combined with effective collaboration between competent professionals, is ultimately what allows the PAS 2035 process to work as intended: improving homes through retrofit while reducing the risk of unintended consequences.

PAS 2035 information from TrustMark | TrustMark PAS 2035:2023 Design Best Practice Guidance | PAS 2035:2023 from BSI

 